ANALISIS PENGUKURAN RELATIVE IMPORTANCE INDEX (RII) UNTUK MENENTUKAN PERINGKAT FAKTOR PENYEBAB KETERLAMBATAN PEKERJAAN KANOPI PROYEK EAST CONNECTION TAXIWAY BANDARA SOEKARNO-HATTA

##plugins.themes.academic_pro.article.main##

Pungky Dharma Saputra
Arif Hidayat

Abstract

The Soekarno-Hatta International Airport is a very busy international airport that requires development to enhance its capacity. The development undertaken involves the taxiway infrastructure. In the East Connection Taxiway Phase I Project at Soekarno-Hatta Airport, an aircraft bridge was constructed above the highway connecting the north and south runways. To mitigate the impact of jet blasts and aircraft engine noise pollution on road users, a canopy with a steel structure was constructed. The project faced delays during implementation, necessitating the identification of the causes of these delays as well as an assessment of their relevance. As a result, the purpose of this study is to calculate the Relative Importance Index (RII) and rank the causes driving project delays. Design Planning (X1), Materials (X2), Labor (X3), Equipment (X4), Financial Conditions (X5), Design Changes (X6), Schedule and Construction Supervision (X7), and Environmental and Social Factors (X8) are among the variables investigated. A quantitative survey with descriptive analysis was used as the research approach. Financial Conditions (X5) is ranked highest with a RII value of 0.864, and Schedule and Construction Supervision (X7) is placed last with a RII value of 0.750, according to the data. This study is planned to serve as a reference for future canopy installations on taxiways that straddle public roadways.

##plugins.themes.academic_pro.article.details##

References

  1. Saputra, P. D., & Y. Latief, 2020. Development of Safety Plan Based on Work Breakdown Structure to Determine Safety Cost for Precast Concrete Bridge Construction Projects. Case Study: Girder Erection with Launching Gantry Method. Civil Engineering and Architecture 8(3): 297-304.
  2. Saputra, P. D., & Y. Latief, 2020. Analysis of Safety Cost Structure in Infrastructure Project of Precast Concrete Bridge based on Work Breakdown Structure. IOP Conf. Series: Materials Science and Engineering 830 022074.
  3. Assaf, S. A., & Al-Hejji, S, 2006. Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357.
  4. Hamzah, N., Khoiry, M. A., Arshad, I., Tawil, N. M., & Che Ani, A. I., 2011. Cause of Construction Delay - Theoretical Framework. Procedia Engineering, 20, 490–495.
  5. Widiantoro, V. Sagita, L. S., Ichsan, M., 2023. Identification Of Factors That Affect the Delay in The Production Cycle Time Of Box Girder. Aip Conf. Proc. 2806, 020117
  6. Kurniawan, I, Saputra, P. D., Safri, and Saputro, R., 2021. Development of Delay Factor Model for Substructure Works in Building Construction. Advances in Engineering Research, 203, 259-264.
  7. Rauzana, A. Zahrah, A, & Dharma, W., 2022. Critical Delay Factor for Construction Projects in Central Aceh District, Indonesia. F1000Research, 11 474
  8. Rauzana, A., Dharma., W., 2022. Causes of delays in construction projects in the Province of Aceh, Indonesia. PLoS ONE 17(1): e0263337.
  9. Asmi, A., Djamaris, A., dan Ihsan, M., 2019. Top Ten Similarity Ranking for Project Delay Factors in Construction Industry. IOP Conference Series: Materials Science and Engineering, 650, 012006.
  10. Arumsari, P. & Karim, M. M., (2020). Identification of Dominant Factors for The Delays in Building Construction Project in Kepulauan Anambas. IOP Conf. Ser.: Earth Environ. Sci. 426 012040
  11. Choong Kog, Y., 2018. Major Construction Delay Factors in Portugal, the UK, and the US. Practice Periodical on Structural Design and Construction, 23(4), 04018024
  12. Auhan, A. M. A. & Rarasati, A. D., 2022. Identification of Project Construction Delay Factors in Depok City, West Java (study ini Department of Housing and Sttlement, Depok City). International Journal of Applied Business and International Management. Vo. 7. No. 3. 30-40
  13. Wuala, H. D., & Rarasati, A. D., 2020. Causes of delays in the construction project for developing Southeast Asia countries. IOP Conference Series: Materials Science and Engineering, 830, 022054.
  14. Susanti, R., Fauziyah, R., & Suwarto, F., 2021. Assesing factors toward construction project delay in Indonesia. IOP Conf. Ser.: Earth Environ. Sci. 700 012064
  15. Alsuliman, J. A., 2019. Causes of delay in Saudi public construction projects. Alexandria Engineering Journal.
  16. Tahmasebinia, F., Song, V., 2022. Significant Factors Causing Delay in the Cambodian Construction Industry. Sustainability, 14, 3521.
  17. E. Safapour, S. Kermanshachi, B. Alfasi, R. Akhavian. 2019. “Identification of Schedule-Performance Indicators and Delay-Recovery Strategies for Low-Cost Housing Projects”, Sustainability 11, 6005
  18. Ramli, M. Z., Malek, M A., Hanipah, M. H., Lin, C. L., Sukri, M. F. M., Zawawi, M. H., Abidin, M. Z. Z., Fuad, N. F. S. M., 2017 Study of factors influencing construction delays at rural area in Malaysia”, International Post Graduate Conference on Applied Science & Physics 2017, IOP Conf. Series: Journal of Physics: Conf. Series 1049, 012017
  19. Rao, B. P., 2016. Delay Analysis of Construction Projects. Journal of IT and Economic Development Department of Civil Engineering, MIT Manipal-576104, Manipal University
  20. Shrivas, A., & Singla, H. K., 2022. Analysis of interaction among th-e factors affecting delay in construction projects using inter-pretive structural modelling approach. Int. J. Constr. Manag.22(8), 1455-1463.
  21. Gunduz, M., Nielsen, Y., & Ozdemir, M., 2015. Fuzzy Assessment Model to Estimate the Probability of Delay in Turkish Construction Projects. Journal of Management in Engineering, 31(4), 04014055
  22. Creswell, John W., 2018. Research Design: Pendekatan Kualitatif, Kuantitatif, dan Mixed.Edisi Keempat. (terj). Pustaka Pelajar: Yogyakarta
  23. Shahsavand, P., Marefat, A., & Parchamijalal, M., 2018. Causes of delays in construction industry and comparative delay analysis techniques with SCL protocol. Engineering, Construction and Architectural Management, 25(4), 497–533.
  24. Tafazzoli, M., & Shrestha, P., 2017. Factor Analysis of Construction Delays in the U.S. Construction Industry. International Conference on Sustainable Infrastructure 2017
  25. Durdyev, S., Omarov, M., Ismail, S., 2017. Cause of Delay in Residential Construction Projects in Cambodia. Cogent Engineering, 4; 1291117.
  26. Latief, I. Q. Bux, Al Saadi, A. M. D. & Rahman, I. A. , 2019. Identification of Delay Factor in Oman Construction Industry, International Journal of Sustainable Construction Engineering and Technology, Vol. 10 No. 1, 34-45
  27. M. S. Islam, B. T. Suhariadi, “Construction delays in privately funded large building projects in Bangladesh”, Asian J Civ Eng 19, 415–429, 2018.
  28. I. Mahamid, A. Bruland, & N. Dmaidi, 2012. “Causes of Delay in Road Construction Projects”, Journal of Management in Engineering, Vol 28, 3.
  29. Elawi, G.S.; Algahtany, M.; Kashiwagi, D., 2016). Sullivan, K. Major Factors Causing Construction Delays in Mecca. J. Adv. Perform. Inf. Value. 7, 1–11.
  30. S. Apipattanavis, K. Sabol, K. R. Molenaar, B. Rajagopalan, Y. Xi, B. Blackard; and S. Patil, “Integrated Framework for Quantifying and Predicting Weather-Related Highway Construction Delays”, Journal of Construction Engineering and Management, Vol. 136, 11, 2010.
  31. P. Ballesteros-Pérez, M. L. del Campo-Hitschfeld, M. A.González-Naranjo and M. C. González-Cruz., 2015. “Climate and construction delays: case study in Chile”. Engineering, Construction and Architectural Management, Vol. 22 No. 6, 596-621
  32. Sustiawan, F. & Husin, A. E., 2021. Analisa RII (Relative Importance Index) Terhadap Faktor-Faktor yang Berpengaruh dalam Memgimplementasikan BIM 4D dan M-PERT Pada Pekerjaan Struktur Bangunan Hunian Bertingkat Tinggi. Jurnal Aplikasi Teknik Sipil. Vol. 19 (4), 417-426.